Kwantlen’s Surrey campus is getting a facelift, funded by $4.9 million from the federal and provincial Knowledge Infrastructure program.
The money will first be put towards the replacement of cladding and windows of building C, said James Meschino, associate director of planning and construction. After that is finished, in January, the rest of the money will go to upgrading other buildings on Surrey campus. According to Meschino, the building has been well maintained over the past 20 years, but wear is starting to show and the cost of maintenance is more then the cost of replacement.
Windows will be replaced with more energy-efficient ones and stucco will be replaced with metal cladding made of zinc, which has a 40-100 year lifespan and will not require painting or maintenance.
Maintenance costs and energy efficiency are not the only goals Kwantlen has for the building. According to an overview of Kwantlen’s Building Expansion projects, Kwantlen wants to reduce its natural gas consumption by 25 per cent and its electricity consumption by 45 per cent for 2010. All of this is in the hopes of getting LEED certified and LEED gold ratings.
LEED (Leadership in Energy and Environmental Design) is a program created by the U.S. Green Building Council that certifies buildings that are built in an efficient and sustainable manner. The awards range from LEED certified to LEED silver, gold and platinum.
Kwantlen’s Cloverdale campus achieved LEED gold status, while the new library at Surrey campus is shooting for the platinum award, said Meschino. He is aiming for LEED gold status for building C.
Building C will be the first to receive a facelift, mainly because it is an administration building and students will not be disturbed. Meschino is treating this project as a test for when construction moves to other buildings. As for what this means for students at Surrey campus, Meschino said they are hoping to create as little disruption as possible and the worst of it will be looking at scaffolding from now until January.
“There’s going to be noise just like any other construction project, but we’re going to work with both the users of the building and the contractors to make sure those noisy activities can happen either off hours or at times that will be less of an issue for users.â€
Comments
Feel free to leave a comment...
For details on how we handle comments, select "Our Comment Policy" from the "About" drop-down menu at the top of the page.
Note: All comments are moderated and must be approved before they are published.